Cadence Minerals #KDNC – Azteca Refurbishment Update
Refurbishment 97% complete and ahead of plan as of 22 August; Operating Licence application submitted Cadence Minerals plc (AIM: KDNC) announces that, as of 22 August 2026, refurbishment of the Azteca processing plant at the Amapá Iron Ore Project had reached 97% weighted physical completion, compared with 95% planned and 87% reported on 10 August […]
Cadence Minerals #KDNC – Refurbishment progresses from 77% to 87%; completion target maintained
Cadence Minerals plc (AIM: KDNC) announces that refurbishment of the Azteca processing plant at the Amapá Iron Ore Project has progressed from 77% to 87% weighted physical completion since the Company’s announcement of 27 July 2026. The programme continues to target operational readiness by the end of August 2026. Commercial operations and shipments remain subject […]
Cadence Minerals #KDNC – Further information regarding General Meeting
Cadence Minerals plc (AIM: KDNC) provides further information ahead of the General Meeting to be held at 10.00 a.m. on 26 August 2026, notice of which was published on 31 July 2026 (the “GM Notice”). The Resolution would give the Board authority to raise capital principally to fund the Pedra Branca do Amapari bridge (the […]
Cadence Minerals #KDNC – Refurbishment progresses from 48% to 77%; operational readiness target maintained
Cadence Minerals plc (AIM: KDNC) is pleased to announce that refurbishment of the Azteca processing plant at the Amapá Iron Ore Project has progressed from 48% to 77% weighted physical completion since the Company’s previous operational update and continues to run ahead of schedule, exceeding the planned 72% completion at the reporting date. Highlights Refurbishment […]
Cadence Minerals #KDNC – Azteca Execution Update
Cadence Minerals plc (AIM: KDNC) announces that refurbishment works at the Azteca plant, part of the Amapá Iron Ore Project in Brazil, are ahead of the current works schedule. The refurbishment programme had reached approximately 48% weighted physical progress, compared with 41% planned progress. The Company continues to target operational readiness by the end of […]
Cadence Minerals #KDNC – Azteca Restart Update
Cadence Minerals plc (AIM: KDNC) announces an update regarding the restart of the Azteca Plant at the Amapá Iron Ore Project in Brazil. Highlights Installation Licence (“LI”) was granted by SEMA/AP and announced on 5 May 2026, authorising approved refurbishment and installation works at Azteca. Following grant of the LI, the offtaker requested clarification on […]
Edison Research – Cadence Minerals: Azteca moves into execution phase
The broader Amapá project remains Cadence’s main long-term value driver. It is a fully integrated iron ore operation with established mine, rail, port and beneficiation infrastructure, a JORC-compliant resource of 276Mt at 38% Fe and a proven and probable reserve of 195.8Mt at 39.3% Fe. The updated pre-feasibility study in 2024 confirmed the potential to […]
Cadence Minerals #KDNC – CEO Kiran Morzaria talks to Alan Green
Alan Green talks to Kiran Morzaria, CEO at AIM listed Cadence Minerals #KDNC which owns a 36% stake in the Amapa iron ore project in Brazil. The Company has just received the Installation Licence from the State of Amapá Environmental Authority which authorises refurbishment, construction and installation works for the Azteca Plant and the larger […]
Cadence Minerals #KDNC – Amapá – Installation Licence Granted
Key regulatory approval unlocks approved site works and advances fully funded Azteca restart toward production, cash flow and the broader Amapá development pathway. Cadence Minerals plc (AIM: KDNC) is pleased to announce that DEV Mineração S.A. (“DEV”), owner and operator of the Amapá Iron Ore Project in Brazil (“Amapá” or the “Project”), has received the […]
Zeus Capital – Cadence Minerals #KDNC Azteca project update
We are tantalizingly close to successful permitting at Azteca. Funding is in place and the technical team to complete the re-commissioning of the plant are on standby. Cadence is confident that commissioning could take place as early as June this year. Azteca will use its free cash flow to fund the full Amapá project through […]