Cadence Minerals (AIM: KDNC) (“Cadence Minerals”, “Cadence”, or “the Company”) is pleased to announce that the Company, together with its joint venture partners Pedra Branca Alliance Pte Ltd (“PBA”) and DEV Mineração S.A. (“DEV”), has executed a binding Prepayment Offtake Agreement (the “Agreement”) with its selected offtake and logistics partner (the “Offtaker”). The Agreement follows the completion of the Offtaker’s technical, legal, and commercial due diligence on the Amapá Iron Ore Project (“Amapá” or the “Project”).

The Agreement provides a US$4.6 million prepayment and working capital facility, enabling the licensing and restart of the Azteca Plant and establishing the commercial framework for the sale of iron ore concentrate.

Highlights

Kiran Morzaria, CEO of Cadence Minerals, commented:

“Executing the binding agreement is a major milestone in our staged approach to bringing Amapá back into production. With due diligence complete and initial funding now available, we can progress the final licensing items ahead of commencing the refurbishment of the Azteca Plant.

The structure ensures Cadence contributes a modest proportion of the capital while retaining full exposure to the near-term cashflow and the wider development of the Project. We now move confidently towards the installation licence and the start of restart activities.”

Commercial Terms

Under the binding agreement, the Offtaker and Cadence will provide a US$4.6 million prepayment facility to restart the Azteca Plant. This funding is provided upfront and will be repaid from future iron ore shipments.

The facility includes US$3.45 million to complete licensing, refurbishment and commissioning of the plant, and US$1.15 million of working capital for logistics and the first shipment.

The first tranche totals US$1.17 million, of which Cadence will contribute US$391,000 and the Offtaker will fund the balance. These funds will be used to obtain the outstanding permits, including the mine installation licence, enabling construction and rehabilitation of the Azteca Plant and the tailings storage facility to begin.

The Offtaker will also fund US$2.43 million in the second tranche and US$1.15 million of working capital. These amounts become available once the relevant construction and production licences are granted and, in the case of working capital, once first production has commenced.

Repayment of the facility will be made per tonne of iron ore shipped, aligning repayments with actual production and early revenues. Cadence will receive its pro-rata share of repayments and marketing income based on its contribution

The prepayment covers all capital and working-capital needs to restart Azteca, meaning no further equity contribution is required from Cadence to bring the plant into production. Marketing arrangements continue on any product shipped above one million tonnes, ensuring long-term commercial alignment with the Offtaker.

Next Steps

The Company and its joint venture partners will now focus on completing the final items required for the mine installation licence, including the supplementary archaeological survey and detailed engineering for the water-reticulation and sewage-treatment systems. These works are expected to conclude in approximately two months, after which the application will move into the formal federal and state environmental approval processes, currently expected to take a further two months.

Subject to the licence being granted, refurbishment and commissioning of the Azteca Plant will begin immediately, with first production and shipment targeted within three months of licence issuance. Once operational, free cashflow from Azteca is expected to fund working capital, ongoing operations, and the initial stages of the DFS and early works for the broader 5.5 Mtpa DR-grade development at Amapá.

About the Amapá Project

The Amapá Iron Ore Project is a fully integrated mine, rail, and port operation in Brazil. It hosts a JORC-compliant Mineral Resource of 276 Mt @ 38% Fe and a Proven and Probable Ore Reserve of 195.8 Mt @ 39.3% Fe. The December 2024 Pre-Feasibility Study confirmed the Project’s potential to produce 5.5 Mtpa of 67.5% Fe DR-grade concentrate, with a post-tax NPV10 of US$1.97 billionand forecast C1 cash costs of US$27.28/dmt FOB Santana.

For further information, contact:

 

Cadence Minerals plc +44 (0) 20 3582 6636
Andrew Suckling
Kiran Morzaria
Zeus (NOMAD & Broker) +44 (0) 20 3829 5000
James Joyce
Darshan Patel

Gabriella Zwarts

Fortified Securities – Joint Broker +44 (0) 20 3411 7773
Guy Wheatley
Brand Communications +44 (0) 7976 431608
Public & Investor Relations